Case Studies
Examples of recent groundworks and surfacing work carried out by D L Collins Ltd across the South East, from tight-access residential foundations to commercial and school resurfacing.
Groundworks Case Studies
Complete groundworks and foundation packages up to DPC. See our groundworks and civil engineering page for the full service overview.
44 square metre extension, complete groundworks package: Farnham, Surrey GU9
Recently completed for a homeowner in Farnham, Surrey GU9.
D L Collins Ltd recently completed a 44 square metre extension, complete groundworks package, for a homeowner in Farnham, Surrey GU9. The work covered the complete groundworks and foundations, up to DPC, for a single-storey rear extension on a tight residential plot with only a narrow side passage for access.
The job
The package covered the whole of the groundworks, from first dig through to a finished base ready for the superstructure:
- ✔Excavation and muck away
- ✔Concrete footings, a 1 metre dig, poured with a pump: C30 concrete
- ✔Cavity brick and block work up to DPC, including internal piers
- ✔A 150 mm block and beam floor
- ✔The existing soil drainage re-routed and extended, with a new inspection chamber
Foundations were a 1 metre dig. C30 concrete was pumped from the road down the side passage, 800 mm at its narrowest point, so the pour could reach the rear garden without taking larger plant through the plot. A 750 mm wide micro digger and grab lorries kept the tight site moving, and bricks, blocks and beams were crane-delivered from the road.
The existing driveway and footpath were protected throughout. The work was completed in six working days.
What this gave the client
One contractor handled the whole package up to DPC, so the homeowner or their builder can take the walls up from a level, finished base. The price was a fixed lump sum. The tight access was designed around, not fought against: access was 800 mm at its narrowest point, so a 750 mm wide micro digger was used, muck was taken away by grab, and C30 concrete was pumped in from the road. The drainage was sorted at the same time as the foundations, the site was kept neat and the existing finishes were looked after, and the work was completed in six working days.
From start to finish, the job was carefully planned and we worked closely with Building Control at every stage. It was delivered on target, on time and on budget.
Builder who’d rather not take on the groundwork? Keen DIYer planning to build your own extension from the foundations up? Tight access or an awkward site? Give us a call before you decide. Speak to the experts in foundations.
Demolition & Site Clearance Case Studies
Since the 1960s, D L Collins Ltd has delivered residential, commercial and industrial demolition, soft strip, facade retention and site clearance across the South East, removing all waste under our waste carrier registration CBDU589386.
Surfacing & Drainage Case Studies
Playground resurfacing, drainage reinstatement and commercial car park cold milling and tarmac resurfacing. See our tarmac, asphalt and surfacing page for more.
Southwater Infant & Junior Academy, Southwater, West Sussex
| Role | Groundworks and surfacing subcontractor |
|---|---|
| Project | Southwater Infant & Junior Academy, Southwater, West Sussex |
| Scope | Playground resurfacing following attenuation tank installation, drainage and tarmac surfacing reinstatement |
| Project value | £48,000 + VAT |
The brief
Following the installation of a new attenuation tank and associated drainage beneath the playground at Southwater Infant & Junior Academy in Southwater, West Sussex, D L Collins Ltd carried out the drainage reinstatement and tarmac playground resurfacing as groundworks and surfacing subcontractor.
What we did
- ✔Segregated the working area across the school site using Heras security fencing to keep the works safe and separate from the school buildings
- ✔Reinstated the drainage and backfilled trench network across the playground
- ✔Hand-laid and raked tarmac into the branching drainage trenches and reinstated sections across the playground
- ✔Compacted trench edges and confined sections with a vibrating plate compactor, working alongside our own mini excavator on site
- ✔Rolled and compacted the wider tarmac resurfacing areas using a ride-on twin-drum roller for a level, even finish
The result
The disturbed trenches and playground areas were reinstated and resurfaced in tarmac, leaving a level, finished playground ready for school use. The work was delivered to a project value of £48,000 + VAT.
Holiday Inn Farnborough, Farnborough, Hampshire
| Principal contractor | Clarke’s Refurbishment Limited |
|---|---|
| Role | Surfacing subcontractor |
| Project | Holiday Inn Farnborough, Farnborough, Hampshire |
| Scope | Cold milling/planing (463 m²), bitumen emulsion bond coat, 40mm 10mm dense surface course tarmac inlay and thermoplastic white lining across front and rear car parks |
| Programme | 48-hour weekend window in October 2025 — completed ahead of schedule |
| Project value | £29,893.91 + VAT |
The challenge
Working as surfacing subcontractor to principal contractor Clarke’s Refurbishment Limited at Holiday Inn Farnborough in Hampshire, D L Collins Ltd was tasked with a full cold milling, tarmac resurfacing and thermoplastic white lining package across 463 m² of the hotel’s front and rear car parks. The works carried a critical 48-hour weekend deadline in October 2025, with liquidated damages at stake if the car parks were not finished and handed back inside that 48-hour window — all while keeping the hotel open for guests, deliveries and day-to-day business.
What we did
- ✔Planned and sequenced the works in detail beforehand and segregated live working areas with cones, barrier tape and pedestrian barriers so the hotel remained safely open throughout
- ✔Cold milled (planed) the existing worn macadam surfacing across four designated front roundabout bay areas (107 m²) and the main rear car park (356 m²) to a clean 40mm milled profile, removing all planing arisings from site under our waste carrier registration CBDU589386 for recycling
- ✔Cleaned and prepared the milled bays and applied a bitumen emulsion bond coat (K140 binder) ahead of laying the new surface
- ✔Inlaid a 40mm consolidated thickness of 10mm dense surface course tarmac — barrowed and hand-raked across the four front roundabout bay areas and machine-laid by midi-paver across the rear car park, tying cleanly into existing kerbs and block-paved aprons
- ✔Compacted the new tarmac using a ride-on twin-drum roller for a dense, level finish
- ✔Completed thermoplastic white lining across all resurfaced areas, including standard parking bays, two accessible disabled bays and a motorcycle bay
The result
We love a challenge. Through careful planning, thorough preparation and sheer determination and organisation from our team, the entire package was completed ahead of schedule inside the 48-hour weekend deadline — avoiding any disruption to hotel trade and eliminating the risk of liquidated damages. Both the front roundabout bays and the rear car park were handed back level, hard-wearing and freshly lined to an agreed contract value of £29,893.91 + VAT.
Prepared to succeed: careful planning, real organisation and a team that delivers ahead of schedule.
Planning a groundworks, demolition or surfacing project?
Call the office nearest you, email us, or use our enquiry form and we will come back to you.
Brighton: 01403 839 167 | Reading: 0118 373 5115
Email: [email protected]